Consultation in the run-up to the political decision
Development of an information sheet for the Municipality of Munich on the occasion of an inspection tour of the building committee to visit automated parking systems, technical preparation and assistance
Planning of the functional tender
Preparation of the tender documents in cooperation with the Department of Construction of the Municipality of Munich and CBP GmbH which took over the building and building services planning.
Basics, general defaults, project preparation and preliminary stages of planning
- Basic investigations
- Examination and check of the project-relevant data
- Preparation and execution of an resident questioning for specifying the requirements regarding the parkable vehicle dimensions
- Determination of the daily variation curve and the user frequency (requirement profile)
- Determination of reservoir and traffic management
- Rough dimensioning of the parking system engineering
- Development of the operational requirements
- Development of the requirements for the air conditioning system
Feasibility studies (parking system engineering / traffic)
- Matching of the possible cubage
- Draft of the basic concept with two solidiums and a central service area
- Positioning of the transfer cabins
- Draft of the basic configuration of the automated parking system
- Indication of the outside boundary lines of the parking system variants
- Draft for surface planning
- Development of the performance characteristics / system logistics
- Development of a test procedure for the characteristic performance parameters und figures
- Development of the configuration structural defaults for the transfer cabins
- Rough dimensioning of the figures for the supply and disposal system
- Development of the service area
- Determination of the necessary fire protection measures
- Development and of the aeration system concept
- Development of a noise control concept
Participation during the project scheduling
- Planning of the construction time (installation of the parking system)
- Monitoring of planning discussions
Restricted procurement procedure on the basis of the VOB/A (awarding and contracting regulation for the construction performances)
- Contribution to the execution of an advance information procedure
European-wide participation competition
- Development of the competitive conditions
- Special requirements for a high reliability of the general contractor
- Special requirements of a high operational reliability of the parking system
- Technical evaluation of the requests to participate
- Evaluation of reference systems with inspection, test parking procedures and measurements
- Participation in the prequalification
Restricted procurement procedure (restricted tendering after a competition contest)
- Development of the functional performance specification for the turnkey construction of the automated underground car park
- Lead management
- Formulation of the project guidelines
- Requirements on underground car park as functional unit
- Detailed work on the parking system technology
- Functional description of all characteristics which can be freely chosen by the offerers
- Detailed preliminary planning and performance specifications of all fixed characteristics
- Determination of the use intensity over the life span
- Specifications for the technically necessary life span of the elements and building groups of the system technology
- Definition of the technical specified condition of the system after the end of the regular contract period of the full service after 20 years
Offer evaluation
- Basic examination of the offers
- Participation in the award of contract - round 1
Participation in the transition to the negotiation procedure
- Modification of the planning and the tender
- Participation in the award of contract - round 2
- Participation and technical documentation of the award decision for the parking system technology
Technical participation in the conclusion of the contract with the general contractor
- Adjustment planning
- Development of the specific contractual specifications
- Specification of special arrangements concerning the parking system technology
Construction surveillance and acceptance
(Dr. Irmscher as public appointed expert of the Berlin Chamber of Commerce for parking and parking systems)
Partial local construction supervision and acceptance, part parking system technology
- Supervision of the final planning documents, recommendations for the technical release of the planning
- Supervision of the construction work (assembly)
- Participation in planning discussions
- Participation in sampling
- Specifications in the course of the realization process
- Participation in the acceptance for safety requirements
- Technical acceptances
- Functional acceptances
- System-logistic acceptances
- Evaluation of the reliability of the system / availability
Recommendation of the main acceptance
Planning of operation and full service
Development of operator concept and the full service concept
- Development of appropriate structures from the economic and technical view with the following elements:
- Economical-technical guidance and monitoring of the operation of the parking system
- User support
- Technical operation including service and maintenance
- Clear delimitation of competences between operators and full service provider
Working out the special requirements for the operation of an automated parking system
- Carrying out of the initial operation and integration of the users
- Mode for the briefing of new parking system users
- Service concept and response times
- Mobility warranties
- Requirements on redundancies
- Planning of the expected technical life cycle of the parking system over 20 years
- Planning of maintenance
- Prognosis of all scheduled and unscheduled events
- Planning of the pallet cleaning
- Participation in the development of a concept for the building inspection
Operating cost calculation
- Determination of the operational consumption values
- Projection of operating costs
System software
- Performance specifications for the event logging, Teleservice and the disturbance management
- Performance specifications for the administrative software of the parking system
Participation in the awarding
- Evaluation of the offers with regards to technical conclusiveness and prices
- System related specifying of the operator concept
- System related specifying of the full service concept
Participation in the elaboration of the full service contract
|